Mangaluru: Rs 32 crore more required for completion of DC office complex at Padil


Daijiworld Media Network – Mangaluru (MS)

Mangaluru, Dec 5: The construction work of the DC office complex of Dakshina Kannada is stalled halfway due to poor planning. The estimate is increasing year by year.

Due to the error of the designer and unwillingness on the part of the people representatives, the work of huge complex began but now the same is limping. Taxpayers’ money is wasted due to unnecessary inclusion in the design.

During the rule of the Congress in 2014, the government approval was given for the new DC office building on the recommendation of the then district in-charge minister Ramanath Rai. However, environmentalists approached the court against cutting of trees that were on the proposed land. After the due process, forest department handed over the land to the revenue department. The work began on the project in March 2018 by housing board.

The building consists of three storeys with an area of 2.26 lac square feet on an area of 5.8 acres. In the beginning the project cost was Rs 41 crore. Later it was increased to Rs 55 crore. As on September 16, 2019 most of the building, roof, doors and railing work was complete. Officials submitted an estimate of Rs 14.5 crore to complete the remaining work in one phase.

Later, some more works were added and the estimated cost list was sent for Rs 29 crore. However, the government did not approve the same. Then the government changed. MLA Umanath Kotian visited the site in 2020. District in-charge minister Sunil Kumar visited the spot in 2022. But there was no progress at all. In August 2023, revenue minister Krishna Byre Gowda held discussion with senior officials.

After the completion of first phase work, an estimate of Rs 29 crore was submitted to the government for approval. However, as this did not get approval even after two years, the estimate is now revised to Rs 32 crore. However, not a single rupee is released even after four months of submission of the latest estimate.

District in charge minister Dinesh Gundu Rao said that revenue minister visited the site two months ago. Discussion will be held with concerned to continue work soon.

Local resident Dayananda H said that there is no signs of the work getting completed. However, the price of land in and around the complex has already sky rocketed due to the DC office complex getting shifted to Padil.

 

 

 

  

Top Stories

Comment on this article

  • rajesh kotian, mangalore / abudhabi

    Wed, Dec 06 2023

    Gents please we have to be serious . This is the public tax payer money being used . Nalin, Vedavyas & Khader should raise their voice in Vidhanasabha to mobilize sufficient fund to accomplish this project as soon as possible

    DisAgree Agree Reply Report Abuse

  • J.F.D Souza, Attavar, Mangalore

    Wed, Dec 06 2023

    All our projects are lagging behind. Can we call it like Mohammed bin Thugluqs regime.

    DisAgree Agree [2] Reply Report Abuse

  • Beowulf, Mangalore

    Tue, Dec 05 2023

    It's better to demolish the building and plant some trees.

    DisAgree [1] Agree [5] Reply Report Abuse

  • nitin, mangalore

    Tue, Dec 05 2023

    scrap dealers are waiting for the tender. Our smart city. QR code enabled Congratulations to us the citizens for permitting and tolerating these wasteful resources . Divided we stand..!

    DisAgree Agree [7] Reply Report Abuse

  • Sandy, Udupi

    Tue, Dec 05 2023

    how much percent?

    DisAgree Agree [2] Reply Report Abuse

  • Rajender, Mangalore

    Tue, Dec 05 2023

    This means Clowns and jokers were involved -- IN A private limited company --constructing say -- a factory such foolish projects cannot be imagined-- -- TAX PAYERS MONEY DOWN THE DRAIN -- TAX PAYER IS apart from Direct tax -- --Indirect tax --who pays GST - and other burdens --- poorest of the poor -- on various day to day items --DC office construction itself is being taken for a ride -- the number one in the district -- what else or what better can be expected-- ONLY BHARAT MATA KI JAI SLOGANS -- BHARAT NAA SHA is taking place--

    DisAgree [1] Agree [4] Reply Report Abuse

  • Saravanabhavana, Murukaveri

    Tue, Dec 05 2023

    What doubble engine did last 5 years of under the leadership of Nalin-ka and Bomma yedd??

    DisAgree [5] Agree [13] Reply Report Abuse

  • Reema, Mangalore

    Tue, Dec 05 2023

    After UP the second place for theft,muder,cheating,rape and bribe will stand for Karnataka soon

    DisAgree [9] Agree [8] Reply Report Abuse

  • Rudolf Rodrigues, Mumbai Mangalore

    Tue, Dec 05 2023

    This was happening 🤯 since long........ skeletons of forefathers falling out!!

    DisAgree [2] Agree [8] Reply Report Abuse

  • Joulan, Mangalore

    Tue, Dec 05 2023

    Then can sell or rent the old premises and cover the costs .

    DisAgree Agree [2] Reply Report Abuse

  • Rudolf Rodrigues, Mumbai Mangalore

    Tue, Dec 05 2023

    🍌 Banana republic; zilch accountability; 75% of people are JHOLACHAP FAKIRS???

    DisAgree [1] Agree [7] Reply Report Abuse

  • G R PRABHUJI, Mangalore

    Tue, Dec 05 2023

    Why DC need posh office? Simple office is more comforts. Government must check all papers and Tender records. Jaise raja,Wise praja.

    DisAgree [2] Agree [8] Reply Report Abuse

  • ayes p, kudla/ksa

    Tue, Dec 05 2023

    OMG poora gulum (it seems 60:40); need Lokayukta raid from bottom to top

    DisAgree [3] Agree [17] Reply Report Abuse

  • KS Mayya, Mangalore/Bangalore

    Tue, Dec 05 2023

    Pay 10% more and hire a profession real estate company you have a nice office. You bring in politicians with strong interests in real estate, you get the concrete confusion that this unfinished building in the middle of forest office represents.

    DisAgree [2] Agree [13] Reply Report Abuse

  • D.Shetty, Mangalore

    Tue, Dec 05 2023

    40% +60% pura kali ...will start again ...

    DisAgree [1] Agree [25] Reply Report Abuse

  • Jossey Saldanha, Raheja Waterfront

    Tue, Dec 05 2023

    60 % Commission ...

    DisAgree [2] Agree [14] Reply Report Abuse


Leave a Comment

Title: Mangaluru: Rs 32 crore more required for completion of DC office complex at Padil



You have 2000 characters left.

Disclaimer:

Please write your correct name and email address. Kindly do not post any personal, abusive, defamatory, infringing, obscene, indecent, discriminatory or unlawful or similar comments. Daijiworld.com will not be responsible for any defamatory message posted under this article.

Please note that sending false messages to insult, defame, intimidate, mislead or deceive people or to intentionally cause public disorder is punishable under law. It is obligatory on Daijiworld to provide the IP address and other details of senders of such comments, to the authority concerned upon request.

Hence, sending offensive comments using daijiworld will be purely at your own risk, and in no way will Daijiworld.com be held responsible.