Mumbai, Nov 22: Train services connecting Mumbai with the Konkan region and south India are likely to face delays and rescheduling due to nightly power and traffic blocks on the Diva-Panvel section from November 22 to 29, Central Railway officials said on Saturday.
According to a Central Railway release, the Mumbai division will operate special blocks between 1.50 am and 4.05 am every night from November 22/23 to November 28/29. The work is being undertaken to remove infrastructure obstructions as part of the Panvel-Kalamboli Coaching Complex project.
The blocks will affect the Up and Down Karjat lines, the Diva-Vasai-Roha-Panvel section and Platform 7 at Panvel railway station.

Several trains will be regulated at stations in Raigad district, including Apta, Jite, Somtane and Poyanje (Mohope), resulting in delays for passengers travelling towards Mumbai, the Konkan region and other destinations in south India.
As per the railway notification, the Mangaluru-Mumbai CSMT Express will be detained for 50 minutes at Apta, while the Madgaon-Mumbai CSMT Konkan Kanya Express will be regulated for 10 minutes at Somtane on journeys commencing between November 22 and 28.
The Thiruvananthapuram-Lokmanya Tilak Terminus (LTT) Superfast Express on November 23 and the Ernakulam-Pune Express on November 24 and 27 will be detained for 109 minutes at Apta.
Similarly, the Ernakulam-Hazrat Nizamuddin Weekly Express on November 25 will be regulated for 60 minutes at Apta, while the Thiruvananthapuram Central-Hazrat Nizamuddin Express on November 28 will face a detention of 109 minutes at the same station.
Several trains departing from Mumbai will also be rescheduled.
The LTT-Madgaon Express will depart 120 minutes behind its scheduled time on November 24, 27, 28 and 29. The LTT-Karmali Superfast Express will be rescheduled by 120 minutes on November 26.
The Daund-Gwalior Express will be delayed by 45 minutes at Poyanje (Mohope) during the night of November 22/23.
Meanwhile, the Solapur-LTT Express will be diverted via Karjat, Kalyan and Thane, with an additional halt at Kalyan, during the night of November 24/25.
Central Railway said the infrastructure work was necessary for the completion and commissioning of the Panvel-Kalamboli Coaching Complex. Once operational, the facility is expected to improve coaching infrastructure, train maintenance arrangements and operational efficiency in the Mumbai railway division.
Passengers have been advised to take note of the revised schedules and plan their journeys accordingly.